This project consists of Division 1, which includes a new wastewater pump station, Division 2, which includes approximately 15,000 linear feet of new force main, and the closeout and decommissioning of the existing Taylors WWTP.
Division 1 includes a 20 MGD pump station consisting of four submersible pumps with 150 HP variable frequency drives; a masonry control building to house electrical gear and control equipment; standby generator system; discharge flow monitoring equipment; and other related appurtenances. Also included are approximately 700 linear feet of 30-inch gravity sewer and related site improvements.
Division 2 includes construction of approximately 960 feet of new 30-inch sewer force main, approximately 13,470 feet of new 24-inch force main, connections at two locations between existing 20-inch, new 24-inch and new 30-inch force mains, construction of approximately 275 feet of new 30-inch gravity sewer line, and connection of new 30-inch gravity sewer to existing 60-inch Enoree River Trunk Sewer.
|